Tag Archives: turbines

Fullabrook noise measurement update

We are still waiting for the report concerning measured noise levels at Fullabrook wind farm and are aware of some residents’ concerns over the length of time this has taken. The measurement of noise at all 12 locations is largely complete … Continue reading

Posted in Posts | Tagged , , , , | Leave a comment

Noise monitoring equipment around Fullabrook now installed

Noise measurement equipment has now been installed at the 12 properties chosen for the noise assessment. North Devon Council appreciates the co-operation of residents, which ensured that the operation went smoothly on Monday 20 February. The equipment will now be … Continue reading

Posted in Noise monitoring, Posts | Tagged , , , , , | Leave a comment

Noise monitoring will begin on Monday

The locations for the noise measuring equipment have now been finalised with local residents and work will begin to measure noise levels on Monday 20 February.  Measurements will be recorded for at least one month to ensure that the complete … Continue reading

Posted in Posts | Tagged , , , , , | Leave a comment

Noise monitoring scheduled to start on Monday 20 February

It has been confirmed that noise assessment around Fullabrook Down Wind Farm can finally start next month. The site developer ESB has informed North Devon Council that Western Power Distribution will allow for the wind farm to operate at full … Continue reading

Posted in Posts | Tagged , , , | 1 Comment

Council requests more noise monitoring points

The council still doesn’t have a definite date for when the Fullabrook Down wind farm will be fully commissioned. However, it is expected that this will be before the end of January. Once the site is fully operational, noise monitoring can … Continue reading

Posted in Posts | Tagged , , , , , | Leave a comment

How we have got to where we are now

In 2004, an application was made to North Devon Council for 22 turbines to be erected, each with up to three megawatts’ capacity. Due to the size of the development, this was referred to the Secretary of State for Business, … Continue reading

Posted in About | Tagged , , , | 4 Comments